Upper Orwell Crossings: Timescales And 2020-21 Funding Deadline

Discussion in 'Upper Orwell Crossings' started by dan5, Aug 10, 2017.

  1. dan5

    dan5ModeratorStaff Member

    Messages:
    1,795
    Funding from the government has been secured until the end of the 2020/21 financial year.

    It is important that consent is obtained in 2017 and work to begin 2019/2020.

    The £77m budget is capped - no further monies from central government. The current cost is now circa £100m instead of the earlier £60m Wet Dock Crossing estimate.

    SCCagendaitemUOCFunding.png
     